Hi, can anyone give me a hint on this issue. 

my trigger: NEW OR UPDATED ROW IN MYSQL

my action: UPDATE SPREADSHEET ROW(S) IN GOOGLE SHEETS

my zap: UPDTAES THE ROW OBTAINED FROM THE TRIGGER  BUT THE UPDATE TAKES PLACE ONE ROW BELOW. I mean.. placing the data on row (n) rather than placing it on row (n+1) 

See screenshots

As you can see… id 1 is pointing to row 2. I need id 1 to match row 1. My first row on the worksheet is a header row and it was formated according to zapiers advice.There is a video explaining How to set up your Google spreadsheet to work with Zapier.

 

My trigger gets this result after testing:

 

Everything is fine except that row has to be 153 NOT 152 because id 152 points to row 153.

The result i get with id 152, row 152 and COL$A 152 is this:

 

bye bye id 151  hello double id152 😭

If there was no header row everything would be smooth but i need the header row.

Where is my mistake?

any hint?

Thanks in advance

Hi @berprado 

Just add a formatter > number > math action before the Google sheet action and add N + 1 (where n is the faulty current row number). Then map the output number to the row number field in Google sheet.


Thank you very much, seems to be working now,🤗