Question

How to update the 8h per day on the Fixed Duration Schedule More


Hello experts, 

I noticed the following situation: 

Schedule Mode set to Fixed Duration

Resource and Project Calendar set to 7.5 hours a week. 

When adding Duration = 1day, it considers the 8h per day instead 7.5h as set per calendar. I exported it to Excel to show the time stamp: 

Image

And if we update the dates it keeps the memory for the time: 

8:00am to 8:30am - as half hour for the 1 day (April 28) 

Image

Is there a reason for this? Can we change this formula? 

Related question is D365 project operations 


0 replies

Be the first to reply!

Reply