I have recurring tasks in Todoist that I’d like to mark as complete forever, that is, stop the recurrence.
The action ‘mark task as completed’ only marks a single recurrence as completed. The action ‘update task’ doesn’t seem to let you update the relevant field.
Any ideas?
Best answer by Sigurdur130
I figured out a workaround using two actions.
Update task: Change the due date. This has the side-effect of removing any recurrence, so now it’s just a regular task, not a recurring one.
Mark as complete.
Functionally, this is the same as marking a recurring task as ‘complete forever’.
Update task: Change the due date. This has the side-effect of removing any recurrence, so now it’s just a regular task, not a recurring one.
Mark as complete.
Functionally, this is the same as marking a recurring task as ‘complete forever’.