We are organizing events.
The trigger is Trello, if a label is put on a card.
The event's data is looked up in a Giigle Sheets table, which also has a date.
The zap after many steps should wait till the event's date -2 days. I use the delay task for that, it is formatter that creates the date data.
This all works fine, but if the event's sdate-2day] is further in time compared to the trigger date, than 1 month, the zap stops with an error message, "Delay date can not be longer than 1 month".
We do have events which are in the next month, so further in time than the zap triggers.
I need the zap to send a reminder email to the client exactly 2 days before the event.
Do you have a suggestion how to work this out?
Thank you.
Cheers, Michael